Schedule Updates

Develop a Time Management Plan that establishes a project schedule that will ensure the execution of outfitting activities are on time and identifies any potential delays that affect outfitting activities.

Advise stakeholders of schedule dates for information that needs to be received in order to complete commodity planning and validation activities and achieve key milestone dates.

Update Schedules monthly to reflect any and all schedule changes since the last published schedule.

Schedule updating may be required at more frequent intervals during times of heightened or time-sensitive activities.

Schedule Updates include a six week look ahead of planned activities, an assessment of work not completed to date and proposed corrective actions, an issues log prioritized with items requiring immediate action, and review of the status of submittals.